110/11/12
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
Additional Modification, Testing for Coal Handling Control System (CHCS) and Protection Work for CHCS Control Equipment during Coal Handling Equipment Phase I Commissioning Stage (SC portion)
|
得標
|
$ 17,783,670
|
|
110/06/29
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
Inspection of Pulverizer System due to the Fire in Unit 1 Pulverizer No. E
|
得標
|
$ 441,000
|
|
110/06/29
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
大林電廠更新改建計畫主發電設備統包採購案 增設DRS On-line Coating 設備之Y型Tie-in管
|
得標
|
$ 1,207,500
|
|
110/06/29
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
Additional Work in Tripper room in Boiler House for Unit 1 and Unit 2 (Boiler Tripper Top of Floor Thickness from 150mm to 175mm)
|
得標
|
$ 2,375,331
|
|
109/02/25
|
台灣電力股份有限公司核能火力發電工程處
台中電廠新建燃氣機組計畫液化天然氣儲槽興建統包工程
|
未得
|
$ 16,373,967,100
|
|
109/02/07
|
台灣電力股份有限公司核能火力發電工程處
大林電廠更新改建計畫主發電設備AVR系統OPS控制功能與資料通訊方式改善
|
得標
|
$ 10,040,940
|
|
108/12/20
|
台灣電力股份有限公司核能火力發電工程處
大林電廠更新改建計畫主發電設備統包採購案緩拆留用臨時輔助鍋爐衍生之運維費用
|
得標
|
-
|
|
108/07/15
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
Contractual Scope Change for Additional Fixed Hold Up Bubble and Defoaming System
|
得標
|
$ 54,600,000
|
|
108/03/08
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
Additional Auxiliary Steam, Demineralized Water and Plant Air Communication Pipes between Talin Power Plant Unit #1, #2 and #6
|
得標
|
$ 98,175,000
|
|
106/08/15
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
Talin Power Plant Renewal Project Power Generating Equipment with Power Block Building and Facilities-Contractual Scope Change of Additional Function of Unit 1 Trip, Unit 2 Runback and UEL Setting Modification
|
得標
|
$ 10,588,462
|
|
105/08/09
|
DEPARTMENT OF NUCLEAR AND FOSSIL POWER PROJECTS TAIWAN POWER COMPANY
Talin Power Plant Renewal Project Power Generating Equipment with Power Block Building and Facilities-Change of Contractual Scope for a Complete Circulating Water Monitoring System
|
得標
|
$ 9,030,000
|